Question: Troy ID: VNU ID: 1 . 1 1 . When translated into a project network, a work package will become A . a single activity

Troy ID:
VNU ID:
1.11. When translated into a project network, a work package will become
A. a single activity
B. a critical path
C. a milestone
D. one or more activities
E. an arrow
I. 12. On a project network, the activity times are derived from the
A. organization breakdown structure
B. project proposal
D. work packages
E. responsibility matrix
C. budget
I.13. An activity that has more than one dependency arrow flowing into it is termed a(n)
A. parallel activity
D. critical path
B. merge activity
C. burst activity
I.14. activities must be comp. independent activity
A. Merge
B. Successor
D. Burst
E. Parallel
C. Predicular activity.
I. 15. Which of the following correctly calc
A. EF - DUR
D. ES - DUR
B.ES-SL
E. LF - SL
C.
I.16. Which of the following will correctly calculate the total slack in an activity?
A. LS - ES
D. LF - EF
B. LF - ES
C. LS - LF
E. Either LS - ES or LF - EF
I.17. In a resource-constrained project, which of the following is most likely to be changed?
A. Project quality
D. Resource levels
B. The budget
C. Scope creep
I.18. How is project scope defined?
E. The completion date
A. The length of your project and how much it will cost
B. What you expect to deliver to your
C. The deliverables or outputs during the customer when the project is complete course of the project
D. The range of resources you have available
E. The range of customer expectations and their capabilities
I.19. Which of the following is NOT considered a project indirect cost?
A. Supervision
B. Equipment
D. Interest
E. Consultants
C. The project manager's salary
I.20. Which of the following is NOT true about project management?
A. It is not limited to the private sector
C. It is a set of tools
E. It focuses primarily on technical processes
B. Many opportunities are available for individuals interested in this career path
D. It improves one's ability to plan, implement and manage activities to accomplish specific organizational objectives
 Troy ID: VNU ID: 1.11. When translated into a project network,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!