Question: TRUE OR FALSE? a) For a given project, we have a precedence network for all activities of the project. All activities not on the shortest
TRUE OR FALSE?
a) For a given project, we have a precedence network for all activities of the project. All activities not on the shortest path are called critical activities.
b) For most organizations, the major component of inventory holding costs is the opportunity cost of the capital.
c) In each step of project crashing, we usually choose critical activities for crashing, but sometime we also choose non-critical activities for crashing in order to reduce the project duration.