Question: True or false questions correct the incorrect segment in short answer 1.( ) Resource leveling is used on projects which are Time-constrained. 2.( ) Heuristics
True or false questions correct the incorrect segment in short answer
1.( ) Resource leveling is used on projects which are Time-constrained.
2.( ) Heuristics are used in resource-constrained projects to develop the near optimal schedule.
3.( ) One of the disadvantages of resource leveling is the increase in the flexibility of the network.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts