True or false questions correct the incorrect segment in short answer

1.( ) Resource leveling is used on projects which are Time-constrained.

2.( ) Heuristics are used in resource-constrained projects to develop the near optimal schedule.

3.( ) One of the disadvantages of resource leveling is the increase in the flexibility of the network.