Question: True or False: The bar representing a 4 - day activity is twice as long as a bar representing a 2 - day activity in

True or False:
The bar representing a 4-day activity is twice as long as a bar representing a 2-day activity in a bar chart. True
Bar charts lost their popularity with the introduction of the Critical Path Method.
Bars in a bar chart must be connected with relationship lines.
A bar representing an activity in a bar chart may not be continuous.
Bar charts and Gantt charts are two different methods of plotting construction projects' schedules.
Bar charts can be loaded with information other than the timeline of the project.
There is one standard way to break down the project into activities for the purpose of creating a bar chart.
True or False: The bar representing a 4 - day

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!