Question: Two alternatives, code-named X and Y, are under consideration at Brahler Corporation. Costs associated with the alternatives are listed below. Alternative X Alternative Y Materials
| Two alternatives, code-named X and Y, are under consideration at Brahler Corporation. Costs associated with the alternatives are listed below. |
| Alternative X | Alternative Y | |
| Materials costs | $45,000 | $45,000 |
| Processing costs | $50,000 | $67,000 |
| Equipment rental | $16,000 | $16,000 |
| Occupancy costs | $21,000 | $38,000 |
What is the differential cost of Alternative Y over Alternative X, including all of the relevant costs?
$149,000
$166,000
$132,000
$34,000