Two alternatives, code-named X and Y, are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below.
| Alternative X | Alternative Y | |
|---|---|---|
| Materials costs | $ 52,000 | $ 75,800 |
| Processing costs | $ 57,100 | $ 57,100 |
| Equipment rental | $ 21,200 | $ 21,200 |
| Occupancy costs | $ 20,400 | $ 30,000 |
What is the financial advantage (disadvantage) of Alternative Y over Alternative X?
Multiple Choice
-
$(167,400)
-
$150,700
-
$184,100
-
$(33,400)