Question: two changes are made: (i) Activity D, Pour Concrete and Install Frame 5 weeks, instead of 4 weeks; (ii) Activity H, Inspect and Test 3
two changes are made: (i) Activity D, Pour Concrete and Install Frame 5 weeks, instead of 4 weeks; (ii) Activity H, Inspect and Test 3 weeks, instead of 2 weeks. Do the Revised Project Network Problem completely, show network figure, a table showing (ES, EF, LF, LS, ST), Critical Path, and Project Duration.