Question: Two international banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved


Two international banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved resulted in the following project information. The "systems integration team" for this project plans to define and manage the project on two levels. The following activities represent an aggregate view, and within each activity is a more detailed view with subtasks and project networks defined. All times are in weeks. Activity Immediate Predecessors A Activity Time 5 B A 8 C A 6 D B, C 3 E C 9 F C 4 G E 3 H E, F 4 I D, G, H 8 a. Choose the correct network for the project. The correct network is -Select- A. B. A C D A B D B E G E G F H F H C. D. A D A B E F G B E H b. Identify the critical path. The critical path is -Select- c. What is the total project completion time? Round your answer to the nearest whole number. weeks - Icon Key D G F H Check My Work (1 remaining)
Step by Step Solution
There are 3 Steps involved in it
To solve this problem well first identify the correct network then determine the critical path and t... View full answer
Get step-by-step solutions from verified subject matter experts