Question: Two jobs must be processed through five machines. Schedule in order to minimize the total makespan. Calculate the total elapsed time to complete both jobs.

Two jobs must be processed through five machines. Schedule in order to minimize the total makespan. Calculate the total elapsed time to complete both jobs.

Use the graphical method.

Job 1 Job 2
Machine Time (hours) Machine Time (hours)
A 3 B 5
B 4 C 4
C 2 A 3
D 6 D 2
E 2 E 6