Question: The table shown is for five jobs to be processed on two Machines - from M1 to M2 . Determine the sequence that minimizes the
The table shown is for five jobs to be processed on two Machines - from M1 to M2 . Determine the sequence that minimizes the total time elapsed from the commencement of processing to the completion, or the makespan. By the use of tabulation method or drawing the Gantt load chart, calculate the machine idle time.
| JOB | PROCESSING TIME (Hrs) | |
| M1 |
M2
| |
| 1 | 5 | 3 |
| 2 | 1 | 6 |
| 3 | 9 | 7 |
| 4 | 3 | 8 |
| 5 | 10 | 4 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock