Question: The table shown is for five jobs to be processed on two Machines - from M1 to M2 . Determine the sequence that minimizes the

The table shown is for five jobs to be processed on two Machines - from M1 to M2 . Determine the sequence that minimizes the total time elapsed from the commencement of processing to the completion, or the makespan. By the use of tabulation method or drawing the Gantt load chart, calculate the machine idle time.

JOB

PROCESSING TIME (Hrs)

M1

M2

1

5

3

2

1

6

3

9

7

4

3

8

5

10

4