Question: Two models are to be produced on an assembly line. The production rate per hour and work content time for model A are 4 and

Two models are to be produced on an assembly

Two models are to be produced on an assembly line. The production rate per hour and work content time for model A are 4 and 27min. The production rate per hour and work content time for model B are 6 and 25 min. Line efficiency is 0.96 and manning level is 1 . Determine the theoretical minimum number of workers on the line. (7 marks) [Total : 25 marks]