Question: Two potential uses are identified for a parcel. One use costs $240,000 to construct and provides an income of $50,000 per year; in order
Two potential uses are identified for a parcel. One use costs $240,000 to construct and provides an income of $50,000 per year; in order to proceed with this use, legal and consulting fees to receive a zoning variance will cost $22,000. Another use cost $310,000 and results in an income of $48,000 per year; due to physical constraints, however, $25,000 must be set aside to provide adequate storm water drainage ponds for this use. If a capitalization rate of 12 percent is used in the first example, and a capitalization rate of 10 percent is used in the second, which use is the highest-and-best use?
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
To determine the highestandbest use of the parcel we need to calculate the net presen... View full answer