Question: Two processes, p 1 and p 2 , arrive at time 0 and start executing using RR scheduling. The total CPU time of p 1

Two processes, p1 and p2, arrive at time 0 and start executing using RR scheduling.
The total CPU time of p1 is 50 time units, and p2 is 30.
The quantum is Q=10.
The context switching time, which follows every Q, is S=1.
The turnaround time of p1 is
The turnaround time of p2 is
The average turnaround time, ATT, is
 Two processes, p1 and p2, arrive at time 0 and start