Question: type it up please 2. Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through H represents a sub-project,
type it up please
2. Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through H represents a sub-project, as shown in the accompanying precedence diagram. F H E G B D The deterministic time for each activity is as follows. Activity Time Activity Time A 5 E 6 B 6 F 4 3 G 8 D 8 H 3 Please answer the following questions: (1) Which path is the critical path? What is the expected duration of the project? (2) What are the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF) and Slack time for each activity