Wofril Corporation considers equipment maintenance to be a mixed cost. The variable component is $.60 per machine hour, computed using the high and low months' data shown below
| Machine Hours | Total Maintenance Cost | |
| January | 270 | $1,162 |
| June | 160 | $1,096 |
What is the fixed cost component of the Total Maintenance Cost?
a. 1000
b. 1129
c. 465
d. 438