Question: Type or paste What are components of a project budget? Summation of control accounts and cost baseline Contingency reserves and work package cost estimate Activity

Type or paste

  1. What are components of a project budget?

Summation of control accounts and cost baseline

Contingency reserves and work package cost estimate

Activity contingency reserves and activity cost estimates

Cost baseline and management reserves

  1. A company orders a radio receiver from a supplier. The supplier substitutes a model that receives more frequencies that the company requires.

Which concept describes this scenario?

Precision

Grade

Tolerance

Quality

  1. A financial company reviews the digital and printed records of clients held by the financial planners; all agreements are reviewed to make sure clients have signed those that involve the transfer of the money

Which process does this scenario represent?

Audit

Retrospective

Quality Report

Scope Baseline

  1. Which diagram shows the strength of relationships between rows and columns of quality control data?

Scatter

Matrix

Affinity

Fishbone

  1. What is the specific range of acceptable results when performing quality control on a project?

Tolerance

Control Limit

Attribute limit

Inspection

  1. Which cost in quality management includes training?

Appraisal

Internal Failure

External Failure

Prevention

question here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!