Question: U Question 7 2 pts If you develop a matrix with each major task listed on the left side and a timeline at the top

U Question 7 2 pts If you develop a matrix with
U Question 7 2 pts If you develop a matrix with each major task listed on the left side and a timeline at the top you are developing which project management tool? A Network Diagram Gantt Chart Work Breakdown Structure Process Flow Chart 2 pts Question 8 If you are someone who has the capacity to effectively manage the negative effects of stress and to bounce back from adversity you are a person who has cognitive ability a stress-free job tenacity retilence