Question: uCertify : GE - - 5 1 0 3 - 5 R 1 - FA - 2 0 2 4 COURSE - Project Management

uCertify :" GE--5103-5R1-FA-2024
COURSE - Project Management Professional (PMP) Based on PMBOK7
The project team has completed the third phase of the project, and the project manager is in a meeting with other key stakeholders to review the project and
discuss its future. Due to several external factors and major risks, they decided to cancel the project. This review and the subsequent decisions are best referred
to as what?
A
Stage gate and phase gate
B
Termination gate and phase end
C
Go-live and kill point
D
Phase gate and kill point
 uCertify :" GE--5103-5R1-FA-2024 COURSE - Project Management Professional (PMP) Based on

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!