Which of the following statements is not true regarding incremental and iterative development approaches?
A Iterative approaches are better used for clarifying potential solutions.
B Both incremental and iterative approaches can use iterations in their development life cycle.
C Both incremental and iterative approaches are used in adaptive projects.
D
The incremental approach is closer to a predictive approach than an iterative approach is.
E
Iterative approaches involve developing and deploying the final solution in pieces.