Question: uCertify GE - - - 5 1 0 3 - ID 1 - SP - 2 0 2 3 [ Based on Project Management Professional
uCertify
GEIDSPBased on Project Management Professional PMP Based on PMBOK
MY LIBRARY
You are a project manager working for a regional hospital company. You have been assigned the responsibility to manage a project that performs monthly security vulnerability assessments and addresses any identified vulnerabilities. You question the assignment because
A This endeavor cannot be considered a project because no start date is specified.
B The recurring nature of the assessment in addition to the lack of a target end date means that this endeavor is not a project at all.
C Security vulnerability assessments do not materially contribute to your organization's system for Value Delivery and should not be considered
D A security vulnerability assessment produces no specific product, so it is not a project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock