Question: undefined Question 2 (25 pts): For the activities listed a. Draw the network diagram and repsresent each activity with its earliest start and earliest finish

undefined Question 2 (25 pts): For the activitiesundefined

Question 2 (25 pts): For the activities listed a. Draw the network diagram and repsresent each activity with its earliest start and earliest finish (like in the box shown) b. Determine the critical path c. Determine the float (slack) for each activity Dependency Float Earliest start Activity Earliest finish Start A A, E Start B, C 5 X 15 Duration (Days) 0 5 3 6 7 8 2 4 8 6 5 5 3 4 0 Activity Start A B D E F G H I J K L M Finish D, F B, E G HI H, F F J, K, L