Question: undefined The following is a network diagram for a certain building project, where A, B, and C are the starting activities and the finishing activity.

undefined The following is a network diagram forundefined

The following is a network diagram for a certain building project, where A, B, and C are the starting activities and the finishing activity. Activities are carried out in weeks. Use the diagram to answer the questions that follow. 20 28 07 A 7 07 15 20 65 1623 H 3 2129 29 32 3 7 15 DB 7 15 2922 0 2 2 5 7 15 25 E 10 15 25 27 2522 F 2 . 2 2729 RA 2527 015 C 15 1025 The activity with a wrong entry is *****