Question: Under statistical process control and process capability analysis, if a process is out-of-control and not capable, the logical next step would be to first... blame
Under statistical process control and process capability analysis, if a process is out-of-control and not capable, the logical next step would be to first...
blame the operator of the process.
concentrate on bringing the process into statistical control.
discontinue using statistical process control (SPC).
concentrate on making the process capable.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
If a process is outofcontrol and not capable during statistical process control SPC and process capability analysis the logical next step would be to ... View full answer

Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock