Question: Under statistical process control and process capability analysis, if a process is out-of-control and not capable, the logical next step would be to first... blame
Under statistical process control and process capability analysis, if a process is out-of-control and not capable, the logical next step would be to first...
blame the operator of the process.
concentrate on bringing the process into statistical control.
discontinue using statistical process control (SPC).
concentrate on making the process capable.