Question: Under the lot - for - lot ( L 4 L ) lot sizing technique as used in a MRP , we would expect which

Under the lot-for-lot ( L 4 L ) lot sizing technique as used in a MRP, we would expect which of the following?
Minimized carrying costs
A consistent lag of supply behind demand
A just in time management philosophy
Minimized set-up costs
 Under the lot-for-lot ( L 4 L ) lot sizing technique

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!