Question: Under the UCC a liquidated damages clause will be enforceable provided: The anticipated loss from a breach would be difficult to prove. The amount agreed

  1. Under the UCC a liquidated damages clause will be enforceable provided:

  1. The anticipated loss from a breach would be difficult to prove.
  2. The amount agreed is reasonable in light of the anticipated or actual harm caused by the.
  3. Both parties are merchants.
  4. A and B but not C.