Question: Under what conditions may a project manager accept a change request? a. If the request has no effect on project objectives, deadlines, or resources b.

Under what conditions may a project manager accept a change request? a. If the request has no effect on project objectives, deadlines, or resources b. If the request has no effect on project objectives, although it has effects on deadlines and resources c. If the request is coming from a valued customer d. If the request is from the Chief Executive Officer