Question: Unit Cost and Cost Assignment, Nonuniform Inputs Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September: Materials Conversion

Unit Cost and Cost Assignment, Nonuniform Inputs

Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September:

Materials Conversion
Units completed 180,000 180,000
Add: Units in ending WIP x Fraction complete 67,000 35,510
(67,000 x 53%)
Equivalent units of output 247,000 215,510
Costs:
Work in process, September 1:
Materials $147,000
Conversion costs 7,875
Total $154,875
Current costs:
Materials $1,206,000
Conversion costs 430,980
Total $1,636,980

Required:

1. Calculate the unit cost for materials, for conversion, and in total for the fabrication department for September. If required, round your answers to the nearest cent.

Unit materials cost $
Unit conversion cost $
Total unit cost $

2. Calculate the cost of units transferred out and the cost of EWIP. Round unit cost value to the nearest cent in intermediate calculations. If required, round final answers to the nearest dollar.

Cost transferred out $
Cost of ending work in process $

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!