Question: Unit Cost and Cost Assignment, Nonuniform Inputs Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September: Materials Conversion
-
Unit Cost and Cost Assignment, Nonuniform Inputs
Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September:
Materials Conversion Units completed 180,000 180,000 Add: Units in ending WIP X Fraction complete 60,000 36,000 (60,000 X 60%) Equivalent units of output 240,000 216,000 Costs: Work in process, September 1: Materials $147,000 Conversion costs 7,875 Total $154,875 Current costs: Materials $1,053,000 Conversion costs 236,205 Total $1,289,205 Required:
1. Calculate the unit cost for materials, for conversion, and in total for the fabrication department for September. If required, round your answers to the nearest cent.
Unit materials cost $fill in the blank 1 Unit conversion cost $fill in the blank 2 Total unit cost $fill in the blank 3 2. Calculate the cost of units transferred out and the cost of EWIP.
Cost transferred out $fill in the blank 4 Cost of ending work in process $fill in the blank 5 -
Unit Cost and Cost Assignment, Nonuniform Inputs
Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September:
Materials Conversion Units completed 180,000 180,000 Add: Units in ending WIP X Fraction complete 60,000 36,000 (60,000 X 60%) Equivalent units of output 240,000 216,000 Costs: Work in process, September 1: Materials $147,000 Conversion costs 7,875 Total $154,875 Current costs: Materials $1,053,000 Conversion costs 236,205 Total $1,289,205 Required:
1. Calculate the unit cost for materials, for conversion, and in total for the fabrication department for September. If required, round your answers to the nearest cent.
Unit materials cost $fill in the blank 1 Unit conversion cost $fill in the blank 2 Total unit cost $fill in the blank 3 2. Calculate the cost of units transferred out and the cost of EWIP.
Cost transferred out $fill in the blank 4 Cost of ending work in process $fill in the blank 5 -
Unit Cost and Cost Assignment, Nonuniform Inputs
Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September:
Materials Conversion Units completed 180,000 180,000 Add: Units in ending WIP X Fraction complete 60,000 36,000 (60,000 X 60%) Equivalent units of output 240,000 216,000 Costs: Work in process, September 1: Materials $147,000 Conversion costs 7,875 Total $154,875 Current costs: Materials $1,053,000 Conversion costs 236,205 Total $1,289,205 Required:
1. Calculate the unit cost for materials, for conversion, and in total for the fabrication department for September. If required, round your answers to the nearest cent.
Unit materials cost Unit conversion cost Total unit cost 2. Calculate the cost of units transferred out and the cost of EWIP.
Cost transferred out Cost of ending work in process