United assembly products (UAP) earned a subcontract to produce a sub-assembly for Honda. UAP was happy to get the contract but wanted to find out the average time to produce the sub-assembly. After looking at their data or the first five units, they found that the first part took 20 hours and the learning curve is 70%. What will be the average time for the 100 units?