Question: Unlike CPM, PERT can use both deterministic and probabilistic activity time estimates. Group of answer choices True False Flag this Question Question 371.5 pts Which
Unlike CPM, PERT can use both deterministic and probabilistic activity time estimates.
Group of answer choices
True
False
Flag this Question
Question 371.5 pts
Which of these is a process used to provide a logical framework for project planning?
Group of answer choices
A. Project Life Cycling
B. Activity Planning
C. Work Breakdown Structure
D. Critical Chain Approach
E. None of the above
Flag this Question
Question 381.5 pts
Which of these is not potential source of errors when managing projects using PERT/CPM?
Group of answer choices
A. Activity time estimates are inaccurate.
B. Project network diagram is incomplete.
C. AOA network diagramming used instead of AON network diagramming.
D. Network diagram incorrectly expresses activities precedence relationships.
E. Critical path does not include major risk events.
Flag this Question
Question 391.5 pts
In terms of managing personnel, projects are just like managing other types of operations.
Group of answer choices
True
False
Flag this Question
Question 401.5 pts
Project management process used to determine if it makes sense to increase costs to save time is referred to as:
Group of answer choices
A. Project Expediting
B. Fast Tracking
C. Activity Crashing
D. Activity Accelerating
E. Aggregation
Flag this Question
Question 411.5 pts
In critical path analysis, the projects critical path is the sequence of activities which have:
Group of answer choices
A. Most nodes
B. Least events
C. Shortest activity times
D. Greatest activity cost
E. Zero slack times
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts