Question: Usage per Lead Time Item Parent (weeks) A - 1 B 2 2 C 3 3 D 4 2 E 5 2 F 3 3
| Usage per | Lead Time | |
| Item | Parent | (weeks) |
| A | - | 1 |
| B | 2 | 2 |
| C | 3 | 3 |
| D | 4 | 2 |
| E | 5 | 2 |
| F | 3 | 3 |
The end product A is made from components B, and C. B is made from D, E, and F. What is the replenishment lead time for A, assuming there are no inventories?
Question 38 options:
|
|
1 week
|
|
|
7 weeks
|
|
|
8 weeks
|
|
|
6 weeks
|