Question: Usage per Lead Time Item Parent (weeks) A - 1 B 2 2 C 3 3 D 4 2 E 5 2 F 3 3

Usage per Lead Time
Item Parent (weeks)
A - 1
B 2 2
C 3 3
D 4 2
E 5 2
F 3 3

The end product A is made from components B, and C. B is made from D, E, and F. What is the replenishment lead time for A, assuming there are no inventories?

Question 38 options:

1 week

7 weeks

8 weeks

6 weeks