Question: Will's Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component Ris made from 2 units of component X and 1

Will's Welded Widgets (WWW) makes its Q Model

Will's Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component Ris made from 2 units of component X and 1 unit of component Y. Component T is made from 1 unit of component V and 3 units of component Z. Using the given information and the beginning inventories 70 units of component T and 170 units of component R, calculate the minimum replenishment time for the 70 Q Models. R Y z Usage per Lead Time Parent (weeks) Item Q 1 6 R 5 5 S 2 4 T 1 X N Y 1 4 V 1 4 Z 5 The cumulative lead time is weeks