Question: Usage per Parent Item Lead Time (weeks) - X-E200 MNR NENWNNW The end product J is made from components K, L, and M. K is

Usage per Parent Item Lead Time (weeks) - X-E200
Usage per Parent Item Lead Time (weeks) - X-E200 MNR NENWNNW The end product J is made from components K, L, and M. K is made from N and O.O is made from P and Q. What is the gross requirement for Q if the company plans to build 10 of its J model? Assume that there are no beginning inventories. 0 0 0 0 0 60 0 0 360 O 120