Question: Use a weighted score model to choose between three projects (A, B, C) for updating an important internal process. The relative weights for each criterion

Use a weighted score model to choose between three projects (A, B, C) for updating an important internal process. The relative weights for each criterion are shown in the following table as are the scores for each project on each criterion. A score of 1 represents unfavorable, 2 satisfactory, and 3 favorable.

Criterion Weight Project
A B C
Cost 20 1 2 3
Risk 20 3 2 1
Opportunity 10 2 1 3
Profitability 10 3 3 1
Sustainability 10 2 1 1
Safety 25 1 2 3
Competitiveness 10 2 2 2

What would your recommendation be if the weight for the safety went down to 10 and the weight of profitability went up to 25?

Suppose instead that method A received a score of 3 for safety. Would your recommendation change under these circumstances?

The vice president of finance has looked at your original scoring model and feels that tax considerations should be included in the model with a weight of 15. In addition, the VP has scored the methods on tax considerations as follows: project A received a score of 3, project B received a score of 2, and project C received a score of 1. How would this additional information affect your recommendation?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock