Question: Use a weighted score model to choose between three projects (A, B, C) for updating an important internal process. The relative weights for each criterion

Use a weighted score model to choose between three projects (A, B, C) for updating an important internal process. The relative weights for each criterion are shown in the following table as are the scores for each project on each criterion. A score of 1 represents unfavorable, 2 satisfactory, and 3 favorable. Criterion Weight Project A B C Cost 20 1 2 3 Risk 20 2 3 1 Opportunity 10 2 1 3 Profitability 10 3 3 2 Sustainability 10 2 1 1 Safety 25 1 2 3 Competitiveness 10 2 2 2

Step by Step Solution

There are 3 Steps involved in it