Question: Use activity costs & overhead provided (see Excel) to you to calculate total project cost. Project overhead is 20% of total WBS activity cost. Using

Use activity costs & overhead provided (see Excel) to you to calculate total project cost. Project overhead is 20% of total WBS activity cost.

Using WBS Outline, AON, and the rules listed below, create a schedule (use dates) in Excel with the below column headings.

WBS Task ID

Task Name

Start Date

Finish Date

Late Start Date

Late Finish Date

Free Slack Days

Slack Days total

Activity Cost
WBS Item
R&D Project Development
Need Survey $ 64,000
Set Product Specs $ 57,600
Shelf life Report $ 19,200
Nutrition Report $ 9,600
Select Fruit Suppliers $ 9,600
Initial Production
Equipment Rehab $ 528,000
Production Trials $ 235,200
Quality Trials $ 86,400
Quality Metrics $ 12,000
Quality Training $ 136,800
Distribution
Market Testing $ 96,000
Package Design $ 31,200
Select Distributors $ 80,000
Legal
Complete FDA Certification $ 43,200
Register Trademark $ 14,400
Prepare Product Launch $ 325,000
#* Activity Predecessor(s) Duration
3 Need survey None 20
4 Set product specs 3 15
5 Shelf life report 4 10
6 Nutrition report 4 5
7 Select fruit suppliers 5, 6 20
9 Equipment rehab 4 30
10 Production trials 7, 9 15
11 Quality trials 10 20
12 Quality metrics 11 5
13 Quality training 12 15
15 Market testing 5, 6 30
16 Package design 15 15
17 Select distributors 5, 6 25
19 Complete FDA certification 7, 15 15
20 Register trademark 7, 15 5
21 Prepare product launch 13, 16, 17, 19FS + 25 days, 20FS + 15 days 15

AON

The critical path is activities 3, 4, 5, 7, 10, 11, 12, 13, 21
# Days
3 20
4 15
5 10
7 20
10 15
11 20
12 5
13 15
21 15
135

Use the information provided below to create a project schedule.

The following days are observed January 1, Martin Luther King day, (third Monday in January), Memorial Day (last Monday in May), July 4th Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26

If a holiday falls on Saturday then Friday will be given as an extra day off, and if it falls on as Sunday then Monday will be given off.

The project team works eight hour days, Monday through Friday.

The project will begin on January 3, 2012

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!