Question: Use activity costs & overhead provided (see Excel) to you to calculate total project cost. Project overhead is 20% of total WBS activity cost. Using
Use activity costs & overhead provided (see Excel) to you to calculate total project cost. Project overhead is 20% of total WBS activity cost.
Using WBS Outline, AON, and the rules listed below, create a schedule (use dates) in Excel with the below column headings.
WBS Task ID
Task Name
Start Date
Finish Date
Late Start Date
Late Finish Date
Free Slack Days
Slack Days total
| Activity Cost | |||
| WBS Item | |||
| R&D Project Development | |||
| Need Survey | $ 64,000 | ||
| Set Product Specs | $ 57,600 | ||
| Shelf life Report | $ 19,200 | ||
| Nutrition Report | $ 9,600 | ||
| Select Fruit Suppliers | $ 9,600 | ||
| Initial Production | |||
| Equipment Rehab | $ 528,000 | ||
| Production Trials | $ 235,200 | ||
| Quality Trials | $ 86,400 | ||
| Quality Metrics | $ 12,000 | ||
| Quality Training | $ 136,800 | ||
| Distribution | |||
| Market Testing | $ 96,000 | ||
| Package Design | $ 31,200 | ||
| Select Distributors | $ 80,000 | ||
| Legal | |||
| Complete FDA Certification | $ 43,200 | ||
| Register Trademark | $ 14,400 | ||
| Prepare Product Launch | $ 325,000 |
| #* | Activity | Predecessor(s) | Duration |
| 3 | Need survey | None | 20 |
| 4 | Set product specs | 3 | 15 |
| 5 | Shelf life report | 4 | 10 |
| 6 | Nutrition report | 4 | 5 |
| 7 | Select fruit suppliers | 5, 6 | 20 |
| 9 | Equipment rehab | 4 | 30 |
| 10 | Production trials | 7, 9 | 15 |
| 11 | Quality trials | 10 | 20 |
| 12 | Quality metrics | 11 | 5 |
| 13 | Quality training | 12 | 15 |
| 15 | Market testing | 5, 6 | 30 |
| 16 | Package design | 15 | 15 |
| 17 | Select distributors | 5, 6 | 25 |
| 19 | Complete FDA certification | 7, 15 | 15 |
| 20 | Register trademark | 7, 15 | 5 |
| 21 | Prepare product launch | 13, 16, 17, 19FS + 25 days, 20FS + 15 days | 15 |
AON
| The critical path is activities 3, 4, 5, 7, 10, 11, 12, 13, 21 | |||||
| # | Days | ||||
| 3 | 20 | ||||
| 4 | 15 | ||||
| 5 | 10 | ||||
| 7 | 20 | ||||
| 10 | 15 | ||||
| 11 | 20 | ||||
| 12 | 5 | ||||
| 13 | 15 | ||||
| 21 | 15 | ||||
| 135 |
Use the information provided below to create a project schedule.
The following days are observed January 1, Martin Luther King day, (third Monday in January), Memorial Day (last Monday in May), July 4th Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26
If a holiday falls on Saturday then Friday will be given as an extra day off, and if it falls on as Sunday then Monday will be given off.
The project team works eight hour days, Monday through Friday.
The project will begin on January 3, 2012