Question: Use data for the following project: table [ [ , Activity,Duration, weeks,Predecessor ] , [ A , Design / Funding , 8 , ]
Use data for the following project:
tableActivity,Duration, weeks,PredecessorADesignFundingBAllocateRenovate Office Space,ACOrder Servers and Network Switches,ADBuild Network,BCEOrder Software,BCFSetup Firewall,EGTest network under full load,FD
Create Gantt chart for the schedule;
Identify Critical time and time Critical Path ;
Construct draw AOA network.
Upload Excel File with the solved problem.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
