Question: Use Excel with formulas to find the solutions Consider the following project management problem: Work the following CPM problem. Please answer the following questions, based
Use Excel with formulas to find the solutions
Consider the following project management problem:
- Work the following CPM problem. Please answer the following questions, based on this information.
| Task | Immediate Predecessor(s) | Duration (Days) |
| A | none | 3 |
| B | none | 4 |
| C | B | 9 |
| D | A | 2 |
| E | B, D | 7 |
| F | D | 3 |
- What is the expected completion time of this project? (Draw the CPM diagram and show the results.)
-
What is critical path through this project?