Question: Use Excel with formulas to find the solutions Consider the following project management problem: Work the following CPM problem. Please answer the following questions, based

Use Excel with formulas to find the solutions

Consider the following project management problem:

  1. Work the following CPM problem. Please answer the following questions, based on this information.
Task Immediate Predecessor(s) Duration (Days)
A none 3
B none 4
C B 9
D A 2
E B, D 7
F D 3
  1. What is the expected completion time of this project? (Draw the CPM diagram and show the results.)
  2. What is critical path through this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!