Question: USE POM OR OM EXPLORER SOFTWARE TO ANSWER THE QUESTION!!!!! A contractor is preparing a bid to install swimming pools at a new housing addition.

USE POM OR OM EXPLORER SOFTWARE TO ANSWER THE QUESTION!!!!!USE POM OR OM EXPLORER SOFTWARE TO ANSWER THEUSE POM OR OM EXPLORER SOFTWARE TO ANSWER THE

A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 34 hours. The contractor estimates a 75 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is nours. (Enter your response rounded to two decimal places.) What is your estimate of the total time for all six pools? The total time for all six pools is hours. (Enter your response rounded to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!