Question: Use the activity data provided DURATION PRECEDENTS A 6 - B 4 - C 3 A D 2 B E 5 B F 10 -

Use the activity data provided

DURATION PRECEDENTS
A 6 -
B 4 -
C 3 A
D 2 B
E 5 B
F 10 -
G 3 E,F
H 2 C,D
I 3 G,H

a) Develop a schedule bar chart. b) Develop an Activity Network Diagram. Make sure to include the early start, early finish, late

start, and late finish of each activity. Indicate the free float and total float of each activity.

c) What is the critical path?