Question: Use the activity table below. Find the project completion time. What is the combined cost of tasks on the critical path only? Activity Predecessor Time:

Use the activity table below. Find the project completion time. What is the combined cost of tasks on the critical path only? Activity Predecessor Time: (weeks) Cost: ($) 1 - 6 6,400 2 - 2 2,500 3 1 4 5,500 4 2 5 6,400 5 3, 4 6 6,600