Question: Use the below description for the next FIVE questions: Consider the following project for constructing a manufacturing plant Immediate Activity Designation Time (in months) predecessor

 Use the below description for the next FIVE questions: Consider the

Use the below description for the next FIVE questions: Consider the following project for constructing a manufacturing plant Immediate Activity Designation Time (in months) predecessor Site development and construction of A 12 factory building Fabrication and B 16 procurement Alignment and installation of C B 7 Machinery Electricity and D A 8 plumbing work Finishing work on E A 6 factory building Interior work of the F C.D.E 4 factory