Question: Use the below description for the next FIVE questions: Consider the following project for constructing a manufacturing plant Activity Designation Immediate predecessor Time ( in

Use the below description for the next FIVE questions:
Consider the following project for constructing a manufacturing plant
Activity
Designation
Immediate predecessor
Time (in months)
Site development and construction of factory building
A
-
12
Fabrication and procurement
B
-
16
Alignment and installation of Machinery
C
B
7
Electricity and plumbing work
D
A
8
Finishing work on factory building
E
A
6
Interior work of the factory
F
C,D,E
4