Question: Use the BERT analysis approach to calculate the project duration for the following project descriptions? Greenfield Elementary School is initiating a project to develop a
Use the BERT analysis approach to calculate the project duration for the following project descriptions?
Greenfield Elementary School is initiating a project to develop a new School Management System SMS to streamline administrative tasks such as student enrolment, attendance tracking, and grade management. The project involves several key activities, each with varying durations due to uncertainties in development and testing.
Activities and Duration Estimates:
The project team has identified the following activities along with their optimistic, most likely, and pessimistic time estimates in days:
Requirements Gathering
Optimistic: days
Most Likely: days
Pessimistic: days
System Design
Optimistic: days
Most Likely: days
Pessimistic: days
Development
Optimistic: days
Most Likely: days
Pessimistic: days
Testing
Optimistic: days
Most Likely: days
Pessimistic: days
Deployment
Optimistic: days
Most Likely: days
Pessimistic: days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
