Question: Use the chart below to answer the question: 3 5 1 100 2 200 4 280 Build Qty 300 200 210 Week Forecast Customer Orders

Use the chart below to answer the question: 3 5 1

Use the chart below to answer the question: 3 5 1 100 2 200 4 280 Build Qty 300 200 210 Week Forecast Customer Orders (committed) Projected on-hand inventory MPS 200 300 100 225 125 ATP Given the standard build quantity of 300, what is the ATP for week 4? None of the above -50 100