Question: Use the critical path method to analyse the following project and answer the questions following: Activity Predecessor Duration A * 1 B A 8 C

Use the critical path method to analyse the following project and answer the questions following:
Activity Predecessor Duration
A *1
B A 8
C A 3
D B,C 4
E C 2
F C 5
G D,E,F 6
What is the early finish of task B?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!