Question: Use the critical path method to analyse the following project and answer the questions following: Activity Predecessor Duration A * 1 B A 8 C

Use the critical path method to analyse the following project and answer the questions following:
Activity Predecessor Duration
A *1
B A 8
C A 3
D B,C 4
E C 2
F C 5
G D,E,F 6
What is the late finish of task E?