Question: Use the data table below to: (1) prepare a CPM diagram for the complete project, (2) list the tasks which are on the critical path,
Use the data table below to: (1) prepare a CPM diagram for the complete project, (2) list the tasks which are on the critical path, and (3) identify the minimum length of time required for the complete project. Also, (4) identify the change in the total length if task G requires an additional 1 day to complete and (5) identify the change in the total length if task I requires an additional 1 day to complete.

task days to complete predecessor tasks ID D 6 B 5 A A N D 8 B E 8 B F 3 D G 1 E H H . 3 F, G 1 4 CF J 1 G1 K 7 HJ