Question: Use the earned value table for Project Makeready to calculate the estimated cost to completion. Activity 7 1 4 2 1 2 8 3 5

Use the earned value table for Project Makeready to calculate the estimated cost to completion.
Activity
7
14
21
28
35
42
49
Plan
% Complete
Install fixtures
325
250
575
100%
Refinish floors
550
85
635
100%
Replace doors
350
275
625
100%
Complete tiling
1,200
565
1,765
80%
Install back door
875
225
1,100
70%
Landscaping
200
350
550
25%
Monthly Plan
325
800
435
1,475
1,440
425
350
5,250
Monthly Act
550
550
550
1,100
1,650
550
1,100
Question 9Select one:
a.
$4,285
b.
$5,250
c.
$7,645
d.
$6,050

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!