Question: Use the following data for problems 37 to 40. Activity Activity Predecessor Optimistic Time Most Likely Time Pessimistic Time A -- 2 5 9 B
Use the following data for problems 37 to 40.
| Activity | Activity Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | -- | 2 | 5 | 9 |
| B | -- | 14 | 15 | 22 |
| C | A | 1 | 7 | 9 |
| D | B | 12 | 18 | 24 |
| E | C, D | 3 | 6 | 9 |
| F | C, D | 10 | 12 | 18 |
| G | E, F | 8 | 19 | 20 |
| H | E, F | 3 | 4 | 5 |
- The critical path for the project?
- A, C, E, H
- B, D, F, H
- B, D, F, G
- All activities are on the critical path due to the variable activity completion times
- The expected time for activity C is?
- 6.33
- 7.02
- 9.00
- 1.06
- What is expected project completion time?
- 55.0
- 64.0
- 71.0
- 43.0
- What is the variance for the project?
- 3.4
- 5.6
- 7.4
- 11.6
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock